Wednesday , October 4 2023

Saba councils discuss four main themes during retreat

The Executive and Island Councils of Saba held a retreat to inform, discuss, and allow the Is­land Council members to reflect on developments and priorities set in four theme areas: infrastruc­ture; the social domain; policies, projects, and legis­lation; and public service.

During the retreat at Queen’s Garden Hotel, the Executive Council provid­ed an update on the vari­ous topics, whereby there was ample opportunity for in-depth discussions and brainstorming with the Is­land Council members.

Many of the topics will again be discussed in a pub­lic meeting of the Island Council slated for late May. In this article is an update on the construction of a new harbor and water bot­tling plant, the continued upgrading of waste man­agement, and the concept of wastewater treatment.

Harbour

The COVID-19 pandemic has caused a great delay in the construction of a new harbor. It affected the geotechnical surveys, which now have been com­pleted. Based on the results of the surveys, significant work has been done on model-testing and refer­ence designs.

The model tests show that the impact of the waves on the new breakwater at the new location at Black Rocks is five times lower than at the Fort Bay Har­bour.

The environmental impact study, which is important for the building permit to be issued by the Dutch government, is also almost complete. The trials for the coral relocation are also complete. The corals are monitored regularly in two different locations to see which environment is most suitable for their growth.

It is still the intention to start the bidding process for the new harbor this year so that construction can start during the first quarter of 2022. The US-based company ATM is drafting the marina design. The facilities will be out­fitted with industry stan­dards to attract high-end traffic. Discussions are on­going with the Ministry of Infrastructure and Water Management I&W and the Ministry of Finance for ad­ditional funding so that a cargo pier and facility can be tendered during this project.

In the meantime, the con­struction of a new road to connect to the new harbor continues. Within a month the excavation works should be completed. The Public Works Department will build the retaining and safety walls for this phase of the road.

The road will not be paved until the harbor project nears completion. The second phase of the road is slated to be tendered lo­cally in the near future. The engineering for electricity, water, and data are ongoing and these will be in place before the harbor project starts.

Commissioner Bruce Zag­ers to further upgrade the overall quality of waste management, to keep working on reducing the output of smoke, and to im­prove the skills of manage­ment and personnel at the waste management facility. The Executive Council ex­plained that many improve­ments have been made in waste management with the training of personnel and better separation of garbage.

All plastics are now re­moved. This has resulted in a reduction of the burn­ing of non-recyclable waste from four to five times per week to once a week, and a larger number of recycla­bles having to be exported. A scale has been installed at the facility to gather sta­tistics about the waste that comes in.

Additionally, the Island Council has requested the Executive branch to re­search the possibility of in­corporating a compostable material project to mitigate the high volume of materi­als to be shipped out.

The efficiency of garbage separation has shown that human capacity is not the main challenge for sustainability, but rather the high cost to have the materials removed from Saba. The Executive Council is work­ing on securing additional funds to offset the high shipping cost.

Areas related to garbage collection are still being re­fined, including a campaign to further educate the com­munity on reducing waste overall by recycling and reusing.

Bottling Plant

The water bottling plant project was also greatly af­fected by the COVID-19 pandemic. The bottling machinery is in the build­ing, and the bottles are also present. An important component for the project is an electric switchboard, which has been built in the Netherlands and will arrive shortly. The remaining in­frastructural works at the facility are being worked on, after which the manu­facturer will finish the in­stallation and commission the plant.

Sewage/wastewater

The Island Council indi­cated during the retreat that it wanted to see more progress in sewage- and wastewater treatment. A sewage processing plant is part of the second phase of the social housing complex. The possibility of connect­ing or expanding to other areas will be looked into.

GIS Saba

 

Ground-breaking Shark Research Conducted
Police assisted in a hiking accident and dismantles a hemp plantation